Dolgellau WwTW
The demolition of a raised steel structure was completed this week on behalf of our client JN Bentley, the works which was located within Dolgellau WwTW involved the dismantling of a raised steel structure, all associated pipes and pumps including the breaking out of the concrete slab and bund walls.
Careful consideration was taken due to the location of the structure being in close proximity to plant and 14 cables situated within the slab below which remained live for the duration of the demolition process.
Works were safely completed ahead of schedule and to the client’s satisfaction with no injuries, incidents, or damages.
Well done to the team involved.